| | CATHODIC PROTECTION SYSTEMS (IMPRESSED CURRENT)FOR |
| | 0,06 | | MB | LOCK MITER GATES |
| | 37 | | stron |
| | 3382 | | ID | UNITED STATES ARMY CORPS OF ENGINEERS |
| | 2001 | | rok |
| | PART 1 GENERAL |
| | 1.1 REFERENCES |
| | 1.2 UNIT PRICES |
| | 1.3 SYSTEM DESCRIPTION |
| | 1.3.1 General Description |
| | 1.3.2 Performance Requirements |
| | 1.3.2.1 First Criterion |
| | 1.3.2.2 Second Criterion |
| | 1.4 SUBMITTALS |
| | 1.5 QUALIFICATIONS |
| | 1.5.1 Organization's Experience |
| | 1.5.2 Contractor's Responsibilities |
| | 1.5.3 Corrosion Expert |
| | 1.6 PRE-INSTALLATION CONFERENCE |
| | 1.7 DELIVERY, STORAGE AND HANDLING |
| | 1.8 PROJECT/SITE CONDITIONS |
| | 1.9 QUALITY CONTROL |
| | 1.9.1 General |
| | 1.9.2 Reporting |
| | 1.10 MODIFICATION OF DESIGN |
| | PART 2 PRODUCTS |
| | 2.1 MATERIALS AND EQUIPMENT |
| | 2.1.1 Direct Current Cables |
| | 2.1.1.1 Anode Lead Cables |
| | 2.1.1.2 Rectifier and Terminal Cabinets Connection Cables |
| | 2.1.2 Cable in Conduit |
| | 2.2 RECTIFIERS AND AUXILIARY EQUIPMENT |
| | 2.2.1 General |
| | SECTION 13113A Page 1 |
| | 2.2.2 Cabinets |
| | 2.2.3 Wheeled Rectifier Cabinets (Alternate 1) |
| | 2.2.4 Stationary Cabinets (Alternate 2) |
| | 2.2.5 Circuit Breakers |
| | 2.2.6 Step-down Transformers |
| | 2.2.7 Rectifier Transformers |
| | 2.2.8 Rectifiers |
| | 2.2.9 Ammeter and Voltmeter |
| | 2.2.10 Current Monitoring Shunt |
| | 2.2.11 Ammeter and Voltmeter Switches |
| | 2.2.12 Control and Instrument Panel |
| | 2.2.12.1 Tap Bars |
| | 2.2.12.2 DC Output Terminals |
| | 2.2.12.3 Components Identification |
| | 2.2.13 Anode Cable Leads |
| | 2.2.14 Surge Arresters |
| | 2.2.15 Wiring Diagram |
| | 2.2.16 Resistor and Anode Terminal Cabinet Wiring Diagram |
| | 2.3 CONDUIT AND FITTINGS |
| | 2.3.1 Nonmetallic Conduit |
| | 2.3.2 Rigid Metal Conduit |
| | 2.3.3 Conduit Fittings and Outlets |
| | 2.4 RESISTOR AND ANODE TERMINAL CABINETS |
| | 2.5 IMPRESSED CURRENT ANODES AND MATERIALS |
| | 2.5.1 General Requirements |
| | 2.5.2 Ceramic Precious Metal Oxide Coated Anodes |
| | 2.5.2.1 Conductive Precious Metal Oxide Ceramic Coating |
| | 2.5.2.2 Anode Substrate Material |
| | 2.5.3 Hi-Silicon Cast-Iron Anodes |
| | 2.5.3.1 Chemical Composition (Nominal) |
| | 2.5.3.2 Electrical Resistivity |
| | 2.5.3.3 Physical Properties (Nominal) |
| | 2.5.4 Ceramic Coated Titanium Anodes (Disk Type) |
| | 2.5.4.1 General |
| | 2.5.4.2 Impact Protection for Disk Anode Cables |
| | 2.5.4.3 Number of Ceramic Coated Titanium Disk Anodes |
| | 2.5.5 Hi-Silicon Cast Iron Button Anodes |
| | 2.5.5.1 General |
| | 2.5.5.2 High-Silicon, Cast-Iron Anodes (Button Type) |
| | 2.5.5.3 Anodes Number |
| | 2.5.5.4 Assembly |
| | 2.5.5.5 Impact Protection for Button Anode Cables |
| | 2.5.6 Ceramic Coated Titanium Segmented Rod Anodes |
| | 2.5.7 Hi-Silicon Cast Iron Sausage Anode Strings |
| | 2.6 IMPACT PROTECTION FOR RODS AND SAUSAGE-STRING ANODES |
| | 2.6.1 PVC Pipe and Metal Couplings |
| | 2.6.2 Protective Angle Irons |
| | 2.6.2.1 PVC Piping |
| | 2.6.2.2 Painting |
| | 2.7 SPARE PARTS |
| | 2.8 SPECIAL TOOLS |
| | 2.9 MARKINGS |
| | 2.9.1 General |
| | 2.9.2 Rectifier Cabinets |
| | SECTION 13113A Page 2 |
| | PART 3 EXECUTION |
| | 3.1 INSTALLATION AND COMMISSIONING |
| | 3.2 WIRING |
| | 3.2.1 Gate Structure at Control Room |
| | 3.2.2 Rectifier on the Lock Wall |
| | 3.2.3 Wiring on the Gate Structure |
| | 3.3 ROD AND SAUSAGE ANODE INSTALLATION |
| | 3.3.1 Metal Pipe Couplings for PVC Pipe |
| | 3.3.2 Assembly of Titanium Rod Anode |
| | 3.3.3 Suspension of Anode Rod or String Assemblies |
| | 3.4 DISK AND BUTTON ANODE INSTALLATION |
| | 3.4.1 General |
| | 3.4.2 Impact Protection Pipes Installation |
| | 3.4.3 Disk Anode Installation |
| | 3.4.4 Button Anode Installation |
| | 3.5 RECTIFIER CABINET INSTALLATION |
| | 3.6 RESISTOR AND ANODE TERMINAL CABINETS INSTALLATION |
| | 3.7 REPAIR OF EXISTING WORK |
| | 3.8 SYSTEM COMMISSIONING |
| | 3.8.1 General |
| | 3.8.2 Insulation Testing |
| | 3.9. SYSTEM COMPONENT CIRCUIT RESISTANCE MEASUREMENT |
| | 3.10 STRUCTURE-TO-REFERENCE CELL POTENTIAL MEASUREMENTS |
| | 3.11 RECTIFIER ADJUSTMENT |
| | 3.11.1 Locations of Structure-to-Reference Cell for Potential Measurements |
| | 3.11.2 Polarization Decay |
| | 3.12 RECORDING OF MEASUREMENTS |
| | 3.13 GUARANTEE |
| | 3.14 OPERATION AND MAINTENANCE INSTRUCTIONS |
| | 3.14.1 Operating Instructions |
| | 3.14.2 Maintenance Instructions |
| | 3.15 TRAINING COURSE |